Shirlington House Renovations

In early 2018 approximately 50% of the apartment renovations have been completed.  With 78% of the work done in occupied apartment homes, the project has moved quickly and with minimal additional vacancy loss.  The remainder of the project will be completed in August 2018.

 
before_kitchen.JPG

BEFORE

after_kitchen.JPG

AFTER

After.JPG

Premium program
Complete date 8/25/18

Includes:

  • Kitchen/Living Space: all standard features, plus: all new cabinets, granite counter tops, pendent lighting, new convectors, washer and dryer in-unit
  • Bathroom: new vanity and top, new faux wood vinyl plank floors

SElect apartment Program
Complete date 2/21/18

Includes:

  • Kitchen and living space: new laminate counter tops, new stainless steel appliances, reuse existing cabinets, new kitchen lights and fixtures, enlarged opening to kitchen, new light fixtures and ceiling fans, entry door hardware, new faux wood plank floors or refinished parquet floors
  • Bathrooms: new vanity top, new mirror, new lights, new shower rod, faucet, and accessories
 
Shirlington-3036  October 05, 2015-Edit.jpg
canopy rendering.PNG
grill patio_in progress.jpg

Corridors
complete date 3/20/18


Lobby/Leasing
complete date 4/17/18

Includes:

  • Package concierge system, lobby lounge, enhanced elevator lobbies, improved laundry rooms, renovated leasing area, new monument signage, improved trash rooms, new LED lights, hallway carpet and paint
  • Revamp the building main entrance by replacing existing storefront with double glazed storefront system, recladding existing canopy ceiling, refinishing existing canopy structure, and specifying new hardscape finishes. 

Fitness center
complete date 3/15/18


Backyard Amenities
completed 12/15/17

Includes: 

  • pool deck and furniture
  • dog park
  • grill patio
  • outdoor seating groups
  • bocce court
 
Arial view.PNG